Sea Lane Improvement Project

Coffee with Andrew
November 9, 2020
Association Funds
November 30, 2020

Sea Lane Improvement Project

The Sea Lane Project is now underway. Sea Lane, Lee Shore, Weather Shore, and Starboard Tack will all be impacted during construction. The project involves new drainage infrastructure, grading, paving, and pathway realignment. We anticipate having the project substancially complete in April 2021. Please note that weather or other unforeseen events may affect the schedule. Click here for map of project area.

We are currently assisting Broad Creek PSD with replacing their waterline in advance of installing our drainage infrastructure. The waterline crew is currently working on Sea Lane between Starboard Tack and Weather Shore. The stormwater pipe crew is currently working on Sea Lane between Starboard Tack and the Sea Lane bridge.

7 Lee Shore is being used for storing materials and equipment. We also installed underground infrastructure along the western property line to convey stormwater from Sea Lane, Weather Shore, Lee Shore and Starboard Tack to the lagoon.

We recommend not scheduling residential construction projects along Sea Lane as entering/leaving properties will be challenging at times. Should you have specific questions about the project, email projectplanner@pdpoa.org or call 843-785-1109.  We will be sending out more specifics on areas of construction and timing through Tidings emails and text alerts. Click here to sign up for Sea Lane Improvement Project alerts.

Click here to sign up for Sea Lane Improvement Project alerts.